Code is the easy part

Going from engineer to lead, writing code stayed the easy part. Delegating, managing up and managing down on tight timelines were the hard parts.

Applies to
Engineers stepping into a lead or management role.
Verified with
Leading about 40 developers as a central tech lead in Singapore, and six engineers as an engineering lead in Toronto, 2021 to 2026.

I've led teams twice: about 40 developers across a suite of government systems in Singapore, and later six engineers at a startup in Toronto. Both times, writing code was the part I was best at and needed least. The hard parts were letting go of the code, telling stakeholders things they didn't want to hear, and keeping a team steady when the date wasn't moving.

  1. Managing upstakeholders, leadership, the date
  2. Youwhere the pressure meets
  3. Managing downthe people doing the work
A lead sits in the middle. Pressure arrives from above; the job is deciding what passes through.

Why delegating is harder than coding

Every reason to keep the work yourself is true in the moment:

Doing it myself
  • faster today
  • built exactly how I'd build it
  • no one to explain it to
  • if it breaks, it's mine

Wins this week, loses the year

Handing it over
  • slower today
  • someone else's approach
  • time spent explaining and reviewing
  • still mine if it breaks

Slower now, a stronger team later

The trade every new lead faces. The left column is always tempting and almost always wrong past a certain team size.

Managing up when the date is fixed

When a timeline was tight, three habits did most of the work:

CallerWhat I didWhy it worked
Trade scope, not qualitycut or phased features instead of skipping tests and reviewa smaller thing that works beats a bigger thing that breaks after launch
Bad news earlyraised a risk the moment I saw it, with options attachedraised early, a risk still leaves room to change the plan
Speak their languageexplained trade-offs as cost, risk and customer impactstakeholders say yes to fewer incidents far more readily than to a refactor
Managing up, under a fixed date.

The first one matters most. When the date can't move, something else has to: scope, or quality. Quality always looks like the cheaper thing to give up, and it never is. So I'd come with a phased plan: what ships on the date, what follows, and what we'd risk if we squeezed in more.

Managing down when the pressure is on

  1. Absorb the pressurestakeholder heat stops with me
  2. Set clear prioritieswhat matters most, what can wait
  3. Jump in on firesunblock directly, then step back
  4. Protect growthmentoring and reviews keep going in a crunch
What the team needs from a lead when the date is close.

What I'd tell a new lead

Measure yourself by what the team ships and by the calls you make about what to leave out, rather than by the code you write. It felt like doing less at first, and it took me a while to see that it was the work.